Gneeves, Millstreet
Client: SWS
Project Details:
11 x Vestas V 52,850kW
4km grid connection
8km site roads
6km Coillte delivery route upgrade
Kilgarvan, Killarney
Client: SWS
Project Details:
15 Vestas V90 3MW
Clonkeen 110kV Sub-Station
15km new access roads
Tursillagh 2, Tralee
Client: Saorgus Energy
Project Details:
8 x Vestas V52 850kW Turbine (6.8 MW)
6km siteroads, crane bases
38kV Substation extension
5km of onsite cabling
Knocknagoum & Cahercullenagh Windfarm
Client: GVM Wind Energy
Project Details:
3.5 kilometres site roads development
Knockawarriga, Abbeyfeale
Client: SWS
Project Details:
9 x Nordex N90 2.5MW
4.5kms new and upgraded site roads
2.5kms cable trenching and laying
Upgrade of public road delivery route
38kV substation
Glenough, Co. Tipperary
Client: ABO-Wind
Project Details:
9 x Nordex N90
4 x N80 turbines
38kV substation
7km internal electric cabling
Upgrade public road delivery route
9km site roads
Aghada – Glanagow, Cork
Client: EBS Networks
Project Details:
4km 220kV underground interconnector
Jointing bays
Pumped Bentonite surround to cables
Cross Cork Harbour - 220kV Interconnector
Client: ESB Networks/NKT Cables/JDContractor
Project Details:
All inter tidal and marine civil works for 4.8 Kilometres sub-sea cabling
Kilgarvan – Phase 2 Sillahertane
Client: SWS
Project Details:
10 Vestas V52 850Kw
9km interconnection cabling
5km site access roads
ESB Power Station, Aghada Long Point, Cork
Client: ESB Networks
Project Details:
1.2kms 220kV underground interconnector
Jointing bays
Pumped Bentonite surround to cables
Kealkill, Bantry
Client: Mukdar Ltd. & Gaoithe Glas Teo
Project Details:
10 x Gamesa G58, 950kW
4.5 upgrade & new site roads
2.2km electrical cabling
38kV electrical substation
Tournafulla & Knockawarriga to Trien Grid Connection
Client: SWS Energy & SSE Renewables
Project Details:
29km underground grid connection
22.5 km on public road
6.5km cross country
Carriganimma Windfarm, Macroom
Client: Carriganimma Community Windfarm
Project Details:
5kms site access roads
Site drainage and water management
Gortahile, Co. Laois
Client: ABO-Wind
Project Details:
8 x Nordex N 90 2.5mW turbines
38kV substation
3.5km site roads
Upgrade public road delivery route
Kilgarvan, Killarney - Phase 1
Client: SWS
Project Details:
15 Vestas V90 3MW
Clonkeen 110kV Sub-Station
15km new access roads
Gortahile, Co. Laois
Client: ABO-Wind
Project Details:
8 x Nordex N 90 2.5mW turbines
38kV substation
3.5km site roads
Upgrade public road delivery route
Glenough, Co. Tipperary
Client: ABO-Wind
Project Details:
9 x Nordex N90
4 x N80 turbines
38kV substation
7km internal electric cabling
Upgrade public road delivery route
9km site roads
Glenough, Co. Tipperary
Client: ABO-Wind
Project Details:
9 x Nordex N90
4 x N80 turbines
38kV substation
7km internal electric cabling
Upgrade public road delivery route
9km site roads
Muingnaminnane, Tralee
Client: Saorgus Energy
Project Details:
14 x Enercon E48 800 kW
4 x Enercon E44 900 kW turbines (14.8 MW)
4.5km new and upgraded site access roads
38kV substation
5.5km cable trenching
Glanlee Substation
Client: Mid Cork Electrical
Project Details:
110Kv Substation
Aghada Power Station, Great Island, Cork
Client: ESBI/ESB Networks
Project Details:
3 km 220kV underground interconnector
Shore and marine civil works for 3.5km harbour crossing
Joint bays, marine/land cable transition bays
Pumped Bentonite surround to cables
Cauteen Ducting
Client: ABO-Wind
Project Details:
Laying 6 Kilometres of 38 kV underground grid infrastructure
Provide grid access for 4 Windfarms to the Cauteen 110 kV substation
Upgrade of the public road access.
Lairg Windfarm, Highlands, Scotland
Client: ABO-Wind
Project Details:
3 x Nordex N80 2.5MW turbines
4km Site access roads along with one bridge
Control building
3km Grid underground grid connection
1.5km Interconnecting cabling
Dromdeveen Windfarm, Co. Limerick
Client: Reirk Enery
Project Details:
4Kms site roads
Glenough Windfarm, Grid Connection
Client: ABO-Wind
Project Details:
20 Kilometres of 38kV underground grid connection from Glenough Windfarm to Cauteen 110kV sub station.
Cross Cork Harbour - 220kV Interconnector
Client: ESB Networks/NKT Cables/JDContractor
Project Details:
All inter tidal and marine civil works for 4.8 Kilometres sub-sea cabling
Glanagow - Raffeen : 220kV Ducting Contract
Client: ESB Networks
Project Details:
7 Kms of 220kV underground ducting Joint bays
Communications chambers
Link boxes
All associated works to connect these two sub-stations.
Grouselodge Windfarm - Grid Connection
Client: ESB Wind Development Ltd.
Project Details:
3 Kms 38kV underground grid connection
Kilgarvan – Phase 2, Inchincoosh
Client: SWS
Project Details:
13 x Nordex N90 2.5Mw
13km interconnecting cabling
110kV sub station extension
8km site access roads on bog up to 7m deep
Cross Cork Harbour - 220kV Interconnector
Client: ESB Networks/NKT Cables/JDContractor
Project Details:
All inter tidal and marine civil works for 4.8 Kilometres sub-sea cabling
Lairg Windfarm, Highlands, Scotland
Client: ABO-Wind
Project Details:
3 x Nordex N80 2.5MW turbines
4km Site access roads along with one bridge
Control building
3km Grid underground grid connection
1.5km Interconnecting cabling
Rathcahill
Client: SSE & Powerteam
Project Details:
38kV Sub-Station
Cappawhite Windfarm Grid Connection
Client: ESB Wind Energy
Project Details:
7 kilometres of 110kV underground grid connection
Wind Farm Projects
As the reserves of fossil fuels around the world are in decline we are being forced to look at alternative means of energy generation. Ireland's geographical location gives us access to an abundance of wind energy.
Wind Farms are an obvious solution to meeting the provision of our future energy needs.
Denis Moriarty The Kerries Limited are committed to embracing the renewable technologies and have successfully delivered projects in this area.
The company has been the main contractor on the following Wind Farm/Energy Projects:
- • Gortahile Windfarm, Laois – 8 x
Nordex N90 2.5Mw
- • Glenough Windfarm, Tipperary – 13 x
Nordex N90 2.5Mw
- • Dromdeveen Windfarm, Limerick – 4 Kms
site access roads
- • Aghada Power Station - Great Island, Cork
– 3Kms underground interconnector, marine crossing
interface
- • Grouselodge Windfarm, Limerick –
2.5Kms underground grid connection
- • Tursillagh 2, Tralee – 8 x Vestas V47
850Kw
- • Gneeves, Millstreet – 11 x Vestas V
52, 850Kw and 4 Km underground grid connection on roads
- • Kealkill, Bantry – 10 x Gamesa G58,
950Kw
- • Glanlee sub station – 110Kv
substation
- • Kilgarvan, Killarney – 15 Vestas V90
3Mw, Clonkeen Sub-station, main civil works, (turbine foundations
not included)
- • Knockawarriga, Abbeyfeale – 9 x
Nordex N90 2.5Mw
- • Tournafulla & Knockawarriga to Trien grid
connection – 29 Km underground grid connection, 22.5Km on
road, 6.5Km cross country
- • Muingnaminnane, Tralee – 18 x Enercon
E44 & E48 850Kw & 900Kw
- • Kilgarvan Phase 2, Killarney – 13 x
Nordex N90 2.5Mw & 10 x Vestas V52 850Kw
- • ESB power station Aghada Long Point, Cork
– 1.2Kms 220Kv underground interconnector
- • Carriganimma Windfarm, Macroom – 5
Kms site access roads, crane pads, Sub-station
- • Knocknagoum & Cahercullenagh Windfarm
– 3.5 Kilometres Site roads development
- • Aghada - Glanagouw, Cork, Bord Gais/ESB networks – 4 Kilometres 220 Kv underground interconnector